BITUMINOUS MEMBRANE WATERPROOFING AND ASPHALT FINISH
Waterproofing application using a bituminous membrane suitable for the subsequent asphalt pouring stage
1 CONCRETE SUBFLOOR
2 PRIMER
Applied with roller, brush, or spray using ECOIMPRIMER, bituminous primer, total consumption 150–200 g/m².
3 WATERPROOFING
Double-layer application of hot-applied elastoplastomeric bituminous membrane (BPP) COVERBOND HP55, with cold flexibility down to –10 °C. The membrane features reinforcement made of continuous filament polyester nonwoven fabric stabilized with glass, rot-proof, suitable for use on bridges, viaducts, and decks.
4 SOLAR-SHIELDING ELEMENT
5 ASPHALT PAVING
6 WATERPROOFING, VERTICAL UPSTAND
Applied with hot-applied elastoplastomeric bituminous membrane (BPP) COVERBOND HP55, cold flexibility –10 °C. Reinforced with continuous filament polyester nonwoven fabric stabilized with glass, rot-proof, suitable for bridges, viaducts, and decks.